A3 latest
May 13, 2010
From RBK Highways
UPDATE
The Kingston by Pass Southbound slip at New Malden Roundabout is scheduled to reopen on Friday 14 May 2010 at 4pm.
TfL say:
The concrete has now been poured at this location. The wearing course will be completed tomorrow after the concrete has cured and the final reinstatement will be completed.
Thames are currently on target to have the slip road re-opened at 4PM tomorrow (14/05/10)
Please note that Thames Water have put in place a mobile VMS informing the road users that there is concrete curing in progress on the slip road.